THE BRIDGE HAS BEEN COMMISSIONED
The 4R-140A
connecting the cities of Fergana and Margilan, built in 1976, was in an
accident due to the fact that the overpass on the highway to "Fergana
city" had not been fully repaired.
This bridge
was included in the 2022 repair program, and the construction and assembly work
was carried out by the Fergana bridge use unitary enterprise.
Today, the
length of the overpass on the PK48+40 section of the 4R-140A highway to
"Fergona city" has been reconstructed to 165 meters in length and 17
meters in width including the footpath.
As a result
of the performed works, the overpass on the highway, which is one of the main
routes connecting the cities of Fergana and Margilan, was completed and
facilities were created for the residents of the region.
Press
service